4/24/20 - Friday

Start of Day 7:00 am -- End of Day 3:00 pm

Technician on Site: (HVAC) Omar, Vincent

Supervisor on site: Robert

Framing - Moved bridging rails

Needed to move 16 bridging rails 1 bay to the right to allow for cooler openings and drops to fit through roof space between conduit and sprinkler lines.


Called structural Engineer about needing to move bridges, he approved moving bridges without any hesitation.

Framing bridge before moving

Framing bridges are bolted from the bottom and nailed into the 2" x 6" member above

Framing bridge before moving

Framing bridges are bolted from the bottom and nailed into the 2" x 6" member above

Minor issue with Blueprints found

Found minor issue with blue prints. The electrical plan didn't show one of the powered exhaust units that is supposed to be installed with this job.

Informed the Mechanical Engineer and Electrical Engineer about the situation, the Electrical engineer said it will not be a problem and he will provide sketches that will handle issue.

The Mechanical and Electrical engineers answered quickly to the email.

Planned next day: We are receiving our framing that are made from Quick Frames. Monday morning we need to load and bring frames to the locations for the installation of the frames. We will spend at least 1-3 days installing the frames.